This service undergoes a process of improving the efficiency and strengthening delivery capabilities of technical teams. Straits can work with you to develop your team or projects in various engineering studies related covering detailed project assessments for the purpose of capital raising, including prospectus and bond issues, and independent valuations for corporate mergers, takeovers or abolishment of conglomerates.

(Purchasing power parity, infrastructure business cases)

Projects

Pagoh Special Economic Zone – Feasibility Study

Project Highlights

Preparation of feasibility study for Pagoh Special Economic Zone, covering four districts (Tangkak, Segamat, Batu Pahat and Muar) of over 700,000 hectares.

 

Scope of Services

  • Analysis of existing infrastructure capacities (water supply, power supply, sewerage, road capacities, river management areas, natural gas supply and telecommunications) and readiness, gaps analysis and preparation of infrastructure improvement proposals

Project Gallery

  • client: Johor Corporation (JCorp)
  • Year Of Complited: Jun 2021 - Sep 2022

Southern Perak Region Comprehensive Development Plan

Project Highlights

Preparation of Comprehensive Development Plan (CDP) for the southern region of Perak, covering four districts (Tanjung Malim, Tapah, Teluk Intan and Bagan Datuk) of over 400,000 hectares.

Scope of Services

  • Analysis of existing infrastructure capacities (water supply, power supply, sewerage, road capacities, river management areas, natural gas supply and telecommunications) and readiness, gaps analysis and preparation of infrastructure improvement proposals.

Project Gallery

  • client: Northern Corridor Implementation Authority (NCIA)
  • Year Of Complited: Feb 2018 - May 2019

The Westin and Hard Rock Hotel, Desaru Coast, Johor

Project Highlights

Engineering design and supervision of civil and structural works for the upgrading of the hotel infrastructure at Desaru Coast, Desaru, Johor, Malaysia.

Scope of Services

  • Provide civil and structural design, tender documentation and construction contract administration.

Project Gallery

  • client: Themed Attractions Resorts and Hotels Sdn Bhd (TARH)
  • Year Of Complited: Ongoing

Teluk Datai Masterplan, Langkawi, Kedah

Project Highlights

Infrastructure masterplanning and engineering design for the 1,000-acre resort township on the island of Langkawi, Kedah, Malaysia

Scope of Services

  • Provided infrastructure master planning, coordination with local authorities and external agencies on the overall (master) infrastructure, including roads, drainage, stormwater management, power supply, water supply, telecommunications and sewerage infrastructure of the entire township.

Project Gallery

  • client: Themed Attractions Resorts and Hotels Sdn Bhd (TARH)
  • Year Of Complited: Ongoing

Seaside Sepang Township, Selangor

Project Highlights

Infrastructure masterplanning and engineering design for a 1,600-acre resort township in Sepang, Selangor, Malaysia.

Scope of Services

  • Provided sustainable infrastructure solution and design solutions, including reclaimed (non-potable) water, grounwdwater supply, renewable energy sources, open access telecommunication infrastructure and green STP.
  • Provided infrastructure master planning, coordination with local authorities and external agencies on the overall (master) infrastructure, including roads, drainage, earthworks, stormwater management, power supply, water supply, telecommunications and sewerage infrastructure of the entire township.

Project Gallery

  • client: Putrajaya Properties Sdn Bhd (subsidiary of Putrajaya Holdings)
  • Year Of Complited: Nov 2016 – Dec 2018

The Malaysia Vision Valley Local Plan 2045 (RTMVV 2045)

Project Highlights

Preparation of Local Plan for the Malaysia Vision Valley (MVV) in Negeri Sembilan, covering three districts (Seremban, Nilai and Port Dickson) of over 150,000 hectares.

Scope of Services

  • Analysis of existing infrastructure capacities (water supply, power supply, sewerage, road capacities, river management areas, natural gas supply and telecommunications) and readiness, gaps analysis and preparation of infrastructure improvement proposals.
  • Preparation of infrastructure strategy and planning for integration into the Local Plan.

Project Gallery

  • client: Negeri Sembilan State Economic Planning Unit
  • Year Of Complited: Sep 2017 - Apr 2018

One & Only Ember Beach Club, Desaru, Johor

Project Highlights

Engineering design and supervision of civil and structural works for the upgrading of the beach club infrastructure along the Desaru Coast, Desaru, Johor, Malaysia.

Scope of Services

  • Provide civil and structural design, tender documentation and construction contract administration.

Project Gallery

  • client: Themed Attractions Resorts and Hotels Sdn Bhd (TARH)
  • Year Of Complited: Ongoing

ISL Mixed Development Township, Johor

Project Highlights

Infrastructure masterplanning and engineering design for a 3,000-acre mixed-development township in Iskandar Puteri, Johor, Malaysia.

 

Scope of Services

  • Provided sustainable infrastructure solution and design, as well as business case studies for unconventional green infrastructure solutions, including reclaimed (non-potable) water, grounwdwater supply, renewable energy sources, open access telecommunication infrastructure and green STP.
  • Provided infrastructure master planning, coordination with local authorities and external agencies on the overall (master) infrastructure, including roads, drainage, stormwater management, power supply, water supply, telecommunications and sewerage infrastructure of the entire township.

Project Gallery

  • client: Iskandar Capital Sdn bhd (subsidiary of Iskandar Investment Berhad)
  • Year Of Complited: July 2017 – Jun 2020

Els Club Desaru, Johor

Project Highlights

Water balance study of inter-pond drainage and irrigation system for the entire golf course to optimise the volume of reclaimed water which are used for golf course irrigation.

 

Scope of Services

  • Provided water balance study, rainfall and runoff analysis, irrigation requirements, and design of inter-pond irrigation system.

Project Gallery

  • client: Themed Attractions Resorts and Hotels Sdn Bhd (TARH)
  • Year Of Complited: Aug 2016 – Apr 2017

Desaru Coast Township, Johor, Malaysia

Project Highlights

Infrastructure masterplanning and engineering design for the 4,500-acre resort township Desaru, Johor, Malaysia.

 

Scope of Services

  • Provided infrastructure master planning, coordination with local authorities and external agencies on the overall (master) infrastructure, including roads, drainage, stormwater management, power supply, water supply, telecommunications and sewerage infrastructure of the entire township.

Project Gallery

  • client: Themed Attractions Resorts and Hotels Sdn Bhd (TARH)
  • Year Of Complited: Nov 2015 – Dec 2016

Technical Due Diligence on an Industrial Building Structure, Bayan Lepas, Penang

Project Highlights

Technical Due Diligence on an Industrial Building Structure, Bayan Lepas, Penang.

 

Scope of Services

  • Technical due diligence (TDD) of an industrial building’s structural integrity.

Project Gallery

  • client: Agilent Technologies
  • Year Of Complited: Sep 2022 – Dec 2022

Large Scale Solar (LSS) Plant, Perak

Project Highlights

Straits provided an in-country technical support for an overseas engineering firm for the development of a 45MW Large-scale solar power plant in Perak. Our services include supporting in drawing development and technical compliance advisory for local authority submissions, including earthwork, roads, drainage, stormwater management, erosion and sediment control plants, as well as mechanical and electrical systems.

Project Gallery

  • Year Of Complited: April 2020

Kazan Smart City, Russia

Project Highlights

  • Awarded directly by the Government of the Republic of Tatarstan, Russia
  • Project was initiated by the President of Tatarstan
  • SCE performed public engagement during design session to gain input for design basis
  • Project won the FIABCI (Russia) Prix D’Excellence Award for best Masterplan Design in 2013
  • Project won the Malaysian Institute of Planners (MIP) Design Excellence Award in 2014

 
Scope of Services

  • Infrastructure master planning for development of 600-hectare green field in Kazan

Project Gallery

  • client: Tatarstan Development Corporation
  • Year Of Complited: Sep 2012 – Dec 2013